SECTOR: Renewables

H&W completed the design and fabrication of a Module Support Frame (MSF) and substation Jacket for E.ON for installation in the Humber Gateway Offshore Windfarm.

  • Services: Technical Services / Fabrication & Construction
  • Client: E.ON
  • Project: E.ON Humber Gateway MSF and Jacket
  • Date Commenced: Qtr 2 2013
  • Date Delivered: Qtr 3 2014
gantry crane

Energy company E.ON awarded the contract for design and fabrication of the Humber Gateway offshore windfarm substation jacket to Harland and Wolff Heavy Industries Ltd.

E.ON, one of the UK’s leading power and gas companies, is developing the 219MW offshore windfarm, located 8km off the East Yorkshire coast, just north of the river Humber. When commissioned, Humber Gateway will be able to provide enough power for approximately 170,000 UK homes.

The H&W scope of work comprised the design and fabrication of the substation jacket (foundation) and piles, totalling circa 1,600 tonnes.

The jacket was completed, ready for installation Q3 2014.

gantry crane
gantry crane

Related Projects

Robin Rigg Offshore Wind Farm

RENEWABLES
  • Repair & Maintenance
  • Fabrication & Construction

Robin Rigg Offshore Wind Farm consisted of 60 Vestas 3.0MW turbines, located off the Dumfries and Galloway coast in the Solway Firth.

Scotrenewables SR2000 Tidal Turbine

RENEWABLES
  • Technical Services
  • Fabrication & Construction

Scotrenewables launch world’s largest tidal turbine.

Bard 1 Transformer Platform and Jacket

RENEWABLES
  • Fabrication & Construction

H&W completed the construction of an offshore wind energy transformer in a joint project.